03-03 0 039-003 |
JORDAN LAWRENCE D + CHERYL B |
309 |
CHESTNUT HILL RD |
25-133M
|
Mechanical |
08/24/2025 |
256.00 |
Approved |
Remove existing 105 btu bioler with tankless coil and two zones of heat with New Yorker CL3-105 boiler with tankless coil and 2 zones of heat.I will repipe supply with sentry zone valves and spiral vent.I will repipe return piping with taco ECM circulator pump and purge. I will run new oil line from oil tank to Beckett burner with new Garber oil filter.I will run new vent pipe from bolier to chimney with draft regulator.I will wire boiler to code |
4W-07 0 032-000 |
SWANBACK CARL E |
66 |
DAVIDSON RD |
Draft
|
Electrical |
|
965.00 |
New |
Installing rooftop railed solar PV 15.58KW and 38 modules. |
11-00 0 028-000 |
KEYSTONE SHOPPES LLC |
179 |
LINWOOD AVE |
Draft
|
Plumbing |
|
73.00 |
Paid |
Final field hook up of an UL-300 approved factory installed wet chemical fire suppression system for the kitchen hood located at Chipotle.
|
16-00 0 069-000 |
SHARR REALTY LLC |
119 |
SOUTH MAIN ST |
Draft
|
Building |
|
852.00 |
Payment Rcvd |
Description of Work Per Sign
1. FRONT ELEVATION (Sign #1): Replacement of existing illuminated sign from 52.21 SQ. FT. to 52.16 SQ. FT.
2. DRIVE-THRU PHARMACY ELEVATION (Sign #2): Installation of a new illuminated sign (17.65 SQ. FT.), no existing sign
3. DRIVE-THRU PHARMACY ELEVATION (Sign #3): Modification of existing non-illuminated letters. Replacing the existing 12 SQ. FT. with new sign to 17.65 SQ. FT.
4. PYLON ELEVATION (Sign #11): Replacement of existing pylon sign faces. It's a direct replacement of 47.29 SQ. FT. of illuminated signage. (like for like) |
02-02 0 001-007 |
FONTANA ANTHONY + KELLY |
78 |
RESERVOIR RD |
Draft
|
Electrical |
|
641.00 |
Payment Due |
Installation of 10.25kW DC PV roof mounted with 25 panels. Existing back-up generator installed. Satellite dish on AR-2 to be re-located by customer. |
06-10 0 018-000 |
SHUMSKI LOVLEY DENISE + RAYMOND KEVIN J |
31 |
HICKORY RD |
Draft
|
Driveway |
|
50.00 |
Paid |
Driveway Construction |
06-06 0 030-000 |
CLEARY JOHN S + KATHRYN A |
191 |
MILLER RD |
25-132M
|
Mechanical |
08/24/2025 |
782.00 |
Approved |
Removing 2 AC condensers and 2 air handlers.
Installing 2 heat pump condensers and 2 new air handlers
Condensers: 2 Bosch BOVA-36RTB-M20S 36,000 BTU heat pump condensers, using R454B refrigerant
Air handlers: one 2 ton Bosch BIVA24RCBM20X air handler for the first floor and one Bosch BIVA36RCBM20X 36,000 BTU for the second floor
|
06-10 0 017-000 |
ALEXANDER PHILIP E + ELAINE M |
27 |
HICKORY RD |
Draft
|
Driveway |
|
50.00 |
Paid |
Driveway Construction |
03-00 0 001-522 |
HIDALGO MATTHEW + VEGA ESPANOL ZULANY |
10 |
JORDAN LN |
Draft
|
CO |
|
|
New |
New Construction (Residential) |
03-00 0 001-521 |
KENYON ROBERT |
12 |
JORDAN LN |
25-15CO
|
CO |
08/22/2025 |
|
Approved |
New Construction (Residential) |
06-16 0 018-000 |
ADKINS RALPH P + MARLENE E |
155 |
BULL HILL RD |
25-107CA
|
COC |
08/20/2025 |
|
Closed |
Emergency boiler replacement
Remove and dispose of existing equipment from premises
Installation of Carrier 140k btu oil-fired boiler w/ tankless coil
Installation of each boiler includes: 1- #60 expansion tank, 1- Watts autofeeder/backflow preventer, 1- mixing valve, 1- Spirovent air eliminator, 3- Grundfos Brute circulator pumps, 1- Taco SR5033 zone panel, 3- Honeywell T4 Pro thermostats, modification of exhaust piping to connect new boiler from existing chimney and new misc. copper piping and fittings to install new boiler. Boiler comes with new burner |
01-11 0 009-18A |
ENGEL THOMAS P + VITALE KRISTEN |
148 |
WOODBINE RD |
25-311B
|
Building |
08/20/2025 |
195.00 |
Approved |
Removal of the existing roofing shingles and installation of new underlayments and shingles (21 sq) |
03-03 0 040-003 |
DWRE CONSTRUCTION LLC |
76 |
RIDGEWOOD DR |
25-313B
|
Building |
08/20/2025 |
438.00 |
Approved |
Remove existing siding Install moisture barrier and tape Install lifetime vinyl siding and accessories
|
03-03 0 040-003 |
DWRE CONSTRUCTION LLC |
76 |
RIDGEWOOD DR |
25-312B
|
Building |
08/20/2025 |
337.00 |
Approved |
Remove existing roofing install plywood seam tape 6 ft of ice and water synthetic felt lifetime architectural shingles and ridge vent |
03-03 0 040-003 |
DWRE CONSTRUCTION LLC |
76 |
RIDGEWOOD DR |
25-131M
|
Mechanical |
08/20/2025 |
195.00 |
Approved |
Boiler Replacement.8500 |
03-09 0 049-000 |
LAKE HAYWARD PROPERTIES LLC |
91 |
LAKE HAYWARD RD |
25-37P
|
Plumbing |
08/20/2025 |
1431.00 |
Approved |
PVC drain waste & vent, Pex domestic hot and cold water piping, PVC radon piping, finish plumbing; Building 3 |
18-00 0 010-000 |
REIL SCOTT K + |
48 |
ELMWOOD HGTS |
25-130M
|
Mechanical |
08/20/2025 |
175.00 |
Approved |
Install A New MST396ST Boiler (10 year warranty), |
03-15 0 001-48A |
ALIGATA MARK S |
83 |
STANDISH RD |
25-310B
|
Building |
08/19/2025 |
53.00 |
Approved |
replacing existing inoperable sliding patio door. |
02-02 0 012-001 |
REID DENNIS + JENNIFER (S) |
175 |
SCOTT HILL RD |
25-27G
|
Fuel Gas |
08/19/2025 |
33.00 |
Approved |
1-120 gallon tank to stub |
20-00 0 019-000 |
GAINES ROBERT + SANDRA J |
135 |
BORETZ RD |
25-128M
|
Mechanical |
08/19/2025 |
357.00 |
Approved |
Installation of a new Mitsubishi 2-1 Ductless Heat Pump One new outdoor unit will be placed |
06-10 0 082-01A |
CZECH JOSEPH S |
24 |
SUNSET BLVD |
Draft
|
Mechanical |
|
641.00 |
Payment Due |
TO REPLACE EXISTING FIRST FLOOR ANDSECOND FLOOR HYDRO-AIR A/C SYSTEMS WITH NEW FIRST CO. AND LENNOX UNIT UNITS. |
03-20 0 025-000 |
ROHON PATRICIA A |
134 |
WATERHOLE RD |
25-129M
|
Mechanical |
08/19/2025 |
175.00 |
Approved |
installation of a medium flushwood wood insert, installed in a masonry fireplace with a 6" stainless steel liner kit per manufacturer specs |
07-02 0 009-000 |
DELMASTRO JEFFREY R + |
407 |
WINDHAM AVE |
25-170E
|
Electrical |
08/19/2025 |
53.00 |
Approved |
complete wiring of 2 zone gas boiler (installed by others) |
01-11 0 009-43A |
PANCAROWICZ DAVID + CAROLYN |
187 |
WOODBINE RD |
25-169E
|
Electrical |
08/19/2025 |
94.00 |
Approved |
Rough and final electrical of addition |
03-07 0 036-014 |
CRUZ RANDY L + NANCY |
52 |
CEDAR LN |
25-172E
|
Electrical |
08/20/2025 |
884.00 |
Approved |
Install (51) 440W Solar panels on the roof. |
03-17 0 51A-000 |
715 MIDDLETOWN ROAD LLC |
715 |
MIDDLETOWN RD |
Draft
|
Electrical |
|
33.00 |
Paid |
Relocate an existing light pole to new location |
20-00 0 054-000 |
FORAN JOHN N |
303 |
AMSTON RD |
25-309B
|
Building |
08/19/2025 |
519.00 |
Approved |
Remodel 5' x 8' existing first floor bathroom. Remove 32" x 60" tub and replace with 32" x 60" shower. Eliminate window from inside the existing tub area. Add bathroom exhaust fan/light. |
4W-05 0 005-038 |
WB SHAW + ASSOCIATES LLC |
48 |
VANCEDARFIELD RD |
Draft
|
Driveway |
|
50.00 |
Payment Due |
Driveway Construction |
02-14 0 003-056 |
PETITTI KURT + KIMBERLY |
55 |
ALFRED DR |
Draft
|
Building |
|
832.00 |
Paid |
Storage Garage 16'x32' built by Carefree Small Buildings - Colchester, CT Structure will sit on 6" of 3/4" stone |
06-16 0 016-01A |
OPALENIK STEVEN D + MICHELE L |
16 |
HILLSIDE LN |
25-127M
|
Mechanical |
08/19/2025 |
620.00 |
Approved |
INSTALLATION OF TWO MITSUBISHI MINI SPLIT SYSTEMS BOTH MODELS MXZ-3D30NLHZ WITH FIVE INDOOR UNITS ALL TOGETHER 3 MODELS MSZ-FX15NL, ONE MSZ-FX06NL AND ONE MSZ-FX09NL |
02-08 0 039-000 |
BECKER JOANNE K + |
181 |
MCDONALD RD |
25-308B
|
Building |
08/19/2025 |
478.00 |
Approved |
Remove old siding and install new siding. 14 squares of siding to be installed. |
03-19 0 029-000 |
GAZDZICKI KIM E |
773 |
MIDDLETOWN RD |
25-307B
|
Building |
08/19/2025 |
94.00 |
Approved |
Remove and replace one patio door, no structural changes. Like for like replacement. |
06-12 0 045-019 |
HUYNH LE + RIOS MABEL |
85 |
DEER RUN DR |
25-171E
|
Electrical |
08/20/2025 |
316.00 |
Approved |
Install (1) Tesla Energy Storage System (13.5 kwh) |
09-00 0 002-000 |
COLCHESTER TOWN OF |
300 |
OLD HARTFORD RD |
Draft
|
Building |
|
33.00 |
Paid |
Install a 31 x 19 hopper window in whole in concrete block wall between concessions and garage. |
20-00 0 071-000 |
BROWN EHREN C |
104 |
BORETZ RD |
25-304B
|
Building |
08/17/2025 |
418.00 |
Approved |
Remove existing shake siding and battens and dispose. Dumpster will be provided on site.
Inspect existing sheathing and repair as needed.
Install house wrap on entire surface being sided.
Install Alside Odyssey 0.44 thickness, double 4" siding. Color to be decided.
White outside corner posts, hidden vent soffit, light blocks, dryer vents, and split blocks included.
All windows and doors will be capped with custom bent aluminum coil covering the j channel.
Remove existing gutters and downspouts and install capping on all faccia and rake boards
|
05-06 0 018-000 0-05A |
ROBERTSON KAREN + FARRELL JORDAN |
512 |
SPRINGBROOK CIR |
25-306B
|
Building |
08/19/2025 |
1127.00 |
Approved |
install a new shower conversion unit ( bathroom 1 ) and install a new tub ( bathroom 2 ) for replacement. no structural changes. |
13-02 0 003-000 |
WILSON MARIA C |
9 |
LAKEVIEW DR |
Draft
|
Zoning |
|
110.00 |
Paid |
shed replacement |
06-08 0 009-000 |
PRESCOTT CINDY |
486 |
OLD HARTFORD RD |
25-106CA
|
COC |
08/15/2025 |
|
Closed |
Roof mounted solar array of 20 panels @ 6.2kw/dc |
05-12 0 001-007 |
RETTIG ADAM T |
47 |
PROSPECT HILL RD |
Draft
|
Building |
|
690.00 |
Paid |
Post and beam pool house 24' x 28' |
05-10 0 005-067 |
GOODEN WHITE CHRISMAE |
162 |
MILL HILL RD |
25-125M
|
Mechanical |
08/14/2025 |
316.00 |
Approved |
Remove and replace the existing boiler in the exact same location and footprint as original with new Crown brand TWB100 boiler, flue pipe and controls. |
|